The final Pluto Train 2 modules for the Scarborough energy project have arrived at the Pluto LNG facility in Karratha in Western Australia, marking a significant milestone for the Woodside Energy’s gas development
The completion of the Pluto Train 2 module program advances the Scarborough energy project towards the targeted delivery of first LNG in 2026.
Since February 2024, a total of 51 modules, weighing a combined 56,000 metric tonnes, have been shipped to Karratha from the module yard in Batam, Indonesia, where they were built.
Expanding the Pluto LNG facility to include a second LNG processing train will serve to process gas from the offshore Scarborough field.
Once operational, Pluto Train 2 will have capacity to process approximately 5 million tonnes of LNG per annum. The expanded Pluto facility includes new domestic gas infrastructure and will have the capacity to supply up to 225 terajoules per day to the …